Lincoln Ave. Grade Separation

BergCM served as Prime Consultant and provided resident engineering, inspection and administration for this $6 million project consisting of a grade separation with A.T.S.F., a cast-in-place post-tensioned vehicular bridge over rail and a separate bridge channel crossing. The project connected the City south of the railroad track with a lesser developed segment north of tracks. Large diameter live gas lines required full-time protection by the contractor. Multiple utility conflicts were resolved by the Resident Engineer. Project was completed with no lost time safety incidents. No claims were associated with this project.